ClosedWorksEuropeanGreen

WPB Lith Activated Carbon Filtration and Extraction (AKW)

Brabant Water NV · 1 lots · 354726
Type
Works
45200000
Estimated value
€ 6,50M
estimated
To deadline
Ongoing
Knock-outs
n/a
exclusion grounds
Award basis
Best price-quality ratio
Assess manuallyconfidence low

Brabant Water NV intends to expand its water production facility in Lith with a new anaerobic activated carbon filtration system and a renovation of the water extraction field. The project is executed as a traditional 2-phase construction team: first a construction team phase in which the design, specifications, and open budget are jointly developed, followed by a UAV phase for execution. The construction team must work within a target budget of €5–10 million, including all construction and commissioning costs, but excluding risk and unforeseen costs. Innovation in the areas of sustainability, material use, safety, and maintenance is explicitly required. The tender focuses on an equivalent collaboration, where the construction partner must offer a market-conform hourly rate and actively contribute to project management.

Works · European procedure

Sustainability countsEuropean
Contracting authority
Contract type
Works
Estimated value
€6,500,000
estimated value
Submission deadline
Ongoing
Scope
European
European procedure
Lots
1
1 lots
Main CPV code
Location
Netherlands
CharacteristicsCPV 45WorksEU tenderGreen / SPPactivated carbon filtrationconstruction teamsustainability

01What is being requested

Brabant Water NV intends to expand its water production facility in Lith with a new anaerobic activated carbon filtration system and a renovation of the water extraction field. The project is executed as a traditional 2-phase construction team: first a construction team phase in which the design, specifications, and open budget are jointly developed, followed by a UAV phase for execution. The construction team must work within a target budget of €5–10 million, including all construction and commissioning costs, but excluding risk and unforeseen costs. Innovation in the areas of sustainability, material use, safety, and maintenance is explicitly required. The tender focuses on an equivalent collaboration, where the construction partner must offer a market-conform hourly rate and actively contribute to project management.

Project Description: Brabant Water intends to expand its water production facility in Lith with a new process step: anaerobic activated carbon filtration, in a new architectural building. Additionally, the water extraction field will be renovated, expanded, and redesigned. The eight existing water extraction cellars will be completely renewed, including the installations. Two new water extraction wells and a water extraction switch building will also be added. Site cables, underground pipes with appendages, the source path, and paving will be renewed and/or adjusted to the new design. These w

45200000€ 6,50MWorks
1WPB Lith Activated Carbon Filtration and Extraction (AKW)€6,500,000

02Exclusion grounds

Exclusion grounds — consult the ESPD
  • No specific exclusion grounds were extracted. In a European tender, the mandatory and discretionary grounds of art. 2.86/2.87 of the Dutch Procurement Act almost always apply — check the European Single Procurement Document (ESPD).

03Value in context

€6,500,000

04Likely competitors

#Likely bidderFitWins
1Heijmans Infra B.V.SME9965×
2Dura Vermeer Infra Regionale Projecten BVSME9958×
3ENGIE Infra & Mobility B.V.SME9769×
4Van Gelder BVSME9753×
5Croonwolter&dros B.V.SME9425×
6Ploegam B.V.SME9322×

05Legal themes that may be relevant here

06Frequently asked questions

What does the 2-phase approach of this project entail?
The project is executed as a 2-phase construction team project. In the first phase, work is carried out jointly on the design (preliminary, final, and technical) and the specifications. After completion of this phase, the construction partner can make an offer for the subsequent trajectory, which is executed according to a traditional UAV-2012 specification.
What is the scope of the target budget?
The target budget is in the order of magnitude between € 5,000,000 and € 10,000,000. This budget includes the costs for the Construction Team phase, the realization phase, commissioning, and internal handover, but excludes the project risk budget and unforeseen costs.
In which areas is innovation expected during execution?
There is explicit room for innovative ideas in the fields of sustainability (such as energy savings and material use), design, safety, and improving the use and maintenance of the installations. Methods for quality, standardization, and cost-effectiveness are also relevant.
What are the main works involved in the renovation of the water extraction field?
The works include the complete renewal of eight existing water extraction cellars including the installations, the realization of two new water extraction wells and a water extraction switch building, as well as the renewal or adjustment of site cables, underground pipes, the source path, and the paving.

Automatically compiled from the official tender data and documents.

07Estimated value versus the market

p25
€ 1,4 mln
median
€ 3,6 mln
p75
€ 9,1 mln
€ 6,5 mln

Gegunde waarden in CPV 45 · werken n=3159