This concerns an EU procurement for the installation of the mechanical installations of a new childcare center in Chaam, whereby the contract is awarded on the basis of the lowest price.

Works · Open · European procedure

EuropeanComplete timeline
Contracting authority
ABG-organisatie
Noord-Brabant
Contract type
Works
Open
Estimated value
Estimate not published
Submission deadline
August 25, 2026
09:00
Scope
European
European procedure
Lots
1
1 lots
Main CPV code
Mechanical installations
Location
Alphen Chaam, Noord-Brabant
CharacteristicsCPV 45WorksEU tenderw-installatienieuwbouwinstallateur

01What is being requested

The assignment concerns the installation of the <strong class='strong'>water installation for the realization of a new childcare center in Chaam with a total area of 3,825 m2gfa.

Through this tender, the contracting authority wishes to contract an installer for the installation of the water installation for the realization of a childcare center in Chaam.

45350000Works
1Water installation contractor Kindcentrum Chaam

02Strategic insight

Strategic insight · AI analysis
Ensure an extremely accurate <strong class='strong'>open budget as the award is based solely on price. Check whether the <strong class='strong'>references for the core competencies exactly meet the area requirements and the five-year term. Note that all <strong class='strong'>signed attachments and the UEA are completed fully and correctly to prevent exclusion.
Read automatically from the tender documents using AI. Always verify against the original documents.

03Points of attention

Important · 5
The assignment is part of a <strong class='strong'>technical and functional coherence with building and electrical engineering assignments.Important
Bidders must enter into a <strong class='strong'>coordination agreement with the building contractor.Important
Failure to complete attachments fully or correctly may lead to <strong class='strong'>exclusion.Important
A <strong class='strong'>verification interview with the intended winner is a condition for the final award.Important
The <strong class='strong'>standstill period is at least 90 days.Important

04Can I take part?

Technical · 3
Core competency 1: experience with the realization and delivery of water installations of an educational building / childcare centers with an area of at least 1,750 m2gfa, not older than five years.Technical
Core competency 2: experience in the realization and delivery of the water installation of an indoor sports facility of at least 560 m2gfa, not older than five years.Technical
Possess valid ISO 9001 and VCA*/VCA** certificates.Technical
Financial · 1
Minimum average total turnover of € 5,300,000 (excl. VAT) realized in the last three financial years (2023, 2024, and 2025).Financial
Professional capability · 1
Registered in a professional and/or trade register.Professional capability

05Exclusion grounds

Exclusion grounds — consult the ESPD
  • No specific exclusion grounds were extracted. In a European tender, the mandatory and discretionary grounds of art. 2.86/2.87 of the Dutch Procurement Act almost always apply — check the European Single Procurement Document (ESPD).

06Award criteria

lowest priceweight n/a

The assessment takes place on the basis of the total tender sum on the tender form (excluding options in attachment 2) and the substantiated open budget.

07Process & timeline

Publication of tender documents
28 mei 2026
Closing period for submitting questions
12 juni 2026, 11.00 uur
Publication of Memorandum of Information
22 juni 2026
Second Memorandum of Information
9 juli 2026, 11.00 uur
Publication of second Memorandum of Information
16 juli 2026
Closing period for submission of the tender
25 augustus 2026, 11.00 uur
Award decision
7 september 2026
Final award
28 september 2026
Start of the assignment
november 2026

08Value in context

Estimate not published

The contracting authority did not publish an estimated value — common for a large share of contracts. The EU threshold for werken is € 5,54 M, for reference.

09Likely competitors

#Likely bidderFitWins
1Croonwolter&dros B.V.SME9125×
2BAM Bouw en Techniek bvSME9034×
3SPIE Nederland B.V.SME8923×
4BINX Smartility B.V.SME8827×
5Heijmans Utiliteit B.V.SME8727×
6Unica Installatietechniek B.V.SME8513×

10Tender documents

Bijlage 8 Bestek met kenmerk T240279-17-BT001a dd 13 mei 2026zipMay 31, 2026 · 84447 KB
uea_591067_20260529122420pdfMay 31, 2026 · 538 KB
Bijlage 9 Concept overeenkomstpdfMay 31, 2026 · 214 KB
TN591067 - EF16 Aankondiging van een opdracht - algemene richtlijn, standaardregeling 20260529140947pdfMay 31, 2026 · 193 KB
Bijlage 2 overzicht optionele optimalisatiespdfMay 31, 2026 · 19 KB
Bijlage 5 Klachtenregeling aanbestedingen ABG-organisatiepdfMay 31, 2026 · 197 KB
bestek algemene voorwaarden Nieuwbouw Kindcentrum Chaam definitief d.d. 13-05-2026pdfMay 31, 2026 · 325 KB
AL W-installateur Kindcentrum Chaam Def 28-5-2026pdfMay 31, 2026 · 715 KB

11Legal themes that may be relevant here

12Frequently asked questions

What is the scope of the works for the water installation?
The assignment concerns the installation of the water installation for a complex consisting of two schools of <strong class='strong'>2,020 m2gfa, a movement space, a GGD consultation agency, and a daycare center with BSO.
How is the coherence between the different construction assignments regulated?
The building works, E-installations, and the water installation are <strong class='strong'>separate assignments. There is a technical and functional coherence whereby the realization is dependent on a coordinated execution of all three components.
What rights does the contracting authority retain if a tender fails?
If a procurement procedure fails, for example due to the absence of an acceptable tender, the contracting authority may <strong class='strong'>terminate or suspend the other procedures without right to compensation for costs.

Automatically compiled from the official tender data and documents.

13Estimated value versus the market

p25
€ 1,4 mln
median
€ 3,6 mln
p75
€ 9,1 mln
deze opdracht

Gegunde waarden in CPV 45 · werken n=3159