AwardedWorksOpen

Reconstruction of Bram Streeflandweg in Renkum

Gemeente Renkum · Open · 1 lots · 342524
Type
Works
45222000
Estimated value
€ 1,90M
awarded
To deadline
Ongoing
Knock-outs
n/a
exclusion grounds
Award basis
Best price-quality ratio
2 criteria
Assess manuallyconfidence high

The Municipality of Renkum is going to reconstruct the Bram Streeflandweg by means of civil engineering works on the public space and the sewer system.

Works · Open · National procedure

Complete timeline
Contracting authority
Contract type
Works
Open
Estimated value
€1,899,400
awarded value
Submission deadline
Ongoing
12:00
Scope
National
National procedure
Lots
1
1 lots
Main CPV code
Location
Netherlands
CharacteristicsCPV 45Works

01What is being requested

The assignment concerns the reconstruction of the Bram Streeflandweg in Renkum, including the public space, the replacement of the wastewater sewerage, and the installation of a rainwater sewer with catch basins.

The Municipality of Renkum is going to reconstruct the Bram Streeflandweg in Renkum. The works consist of the reconstruction of the public space, the replacement of the existing wastewater sewerage, and the installation of a rainwater sewer with catch basins. This concerns the Bram Streeflandweg from the Bennekomseweg to the intersection with the Van Ingenstraat.

45222000Works
101

02Outcome

Awarded

G. van Verseveld Grond- en Straatwerk B.V.

Award value
€1,899,400
Bidders
2

03Strategic insight

Strategic insight · AI analysis
When calculating, focus on the SROI obligation of 5% of the wage bill. Take the earthwork balance into account for the ratio between sand and humus-retaining soil. Check the specifications of the concrete footings and the correct color for the finish.
Read automatically from the tender documents using AI. Always verify against the original documents.

04Points of attention

Important · 4
The SROI requirement remains maintained at 5% of the wage bill.Important
The acceptance costs for transport to a facility are included in accordance with the Standard RAW Provisions 2020.Important
The start date of the works will be determined in consultation.Important
The high-pressure gas pipeline is out of service.Important

05Award criteria

Dubotool0

The achieved fictitious discount from the Dubotool calculation.

Tender price100

The tender price in the specifications excl. the fictitious discount from the Dubotool.

06Process & timeline

Deadline for requests for additional information
22/07/2024 12:00 +02:00
Deadline for the receipt of tenders
22/08/2024 12:00 +02:00
Opening date
22/08/2024 12:15 +02:00
Start date
18/09/2024
End date of the duration
13/06/2025

07Value in context

Estimate not published

The contracting authority did not publish an estimated value — common for a large share of contracts. The EU threshold for werken is € 5,54 M, for reference.

08Bidders in this segment

#Likely bidderFitWins
1Heijmans Infra B.V.SME9965×
2BAM Infra B.V.SME9877×
3Van Gelder BVSME9853×
4Dura Vermeer Infra Regionale Projecten BVSME9858×
5Den Ouden Aannemingsbedrijf B.V.SME9823×
6Gebrs. Kurvers B.V.SME9819×

09Tender documents

TN476223 - EF29 Aankondiging gegunde opdracht - algemene richtlijn, standaardregeling 20240927084823pdfSep 27, 2024 · 10 KB
Nota van inlichtingen 2024-08-06-1pdfAug 6, 2024 · 2 KB
RNK 07-00 - 13 Riool doorsneden en detailspdfJul 26, 2024 · 385 KB
NVI bij bestek 2022-15zipJul 25, 2024 · 235 KB
Nota van inlichtingen 2024-07-25-2pdfJul 25, 2024 · 12 KB
Reconstructie Bram StreeflandwegzipJul 8, 2024 · 59693 KB
TN476223 - EF16 Aankondiging van een opdracht - algemene richtlijn, standaardregeling 20240708144359pdfJul 8, 2024 · 9 KB

10Legal themes that may be relevant here

11Frequently asked questions

What does the reconstruction of the Bram Streeflandweg concretely entail?
The works include the reconstruction of the public space, the replacement of the existing wastewater sewerage, and the installation of a rainwater sewer with catch basins. It concerns the section from the Bennekomseweg to the intersection with the Van Ingenstraat.
Which specific works are part of the assignment?
The assignment includes, among other things, implementing traffic measures, clearing a high-pressure gas pipeline (approx. 400 m1), breaking up paving elements (approx. 9,000 m2), installing a separate sewer system (approx. 870 m1), and applying street works (approx. 8,500 m2).
What is the obligation regarding the SROI deployment?
The requirement for SROI deployment remains maintained at 5% of the wage bill.
Who is responsible for the costs of the meetings for the contracting authority?
The costs for items such as rent and coffee for the contracting authority are for the account of the contracting authority.
How is communication with residents and stakeholders arranged?
Residents and stakeholders will receive a single letter at the start of the work by the work unit. However, account must be taken of sending letters in multiple phases.

Automatically compiled from the official tender data and documents.

12Estimated value versus the market

p25
€ 1,4 mln
median
€ 3,6 mln
p75
€ 9,1 mln
€ 1,9 mln

Gegunde waarden in CPV 45 · werken n=3159