This procurement framework describes an open procedure (works) for the renovation of the Sluisjesdijk (SLDK) sludge processing plant within the framework of Project Sluisjesdijk 2.0. The assignment focuses on an integrated, step-by-step renewal of the technical installations that are nearing the end of their service life, while maintaining the continuity of sludge processing during the works. The approach is based on a construction team model, involving a collaborative verification and design agency, with the possibility to outsource sub-processes to specialized contractors. The total value of the assignment is currently unknown, and the deadline has not been specified.

Works · Open · European procedure

European
Contracting authority
Contract type
Works
Open
Estimated value
Estimate not published
Submission deadline
Ongoing
Scope
European
European procedure
Lots
1
1 lots
Main CPV code
Location
Netherlands
CharacteristicsCPV 45WorksEU tender

01What is being requested

This procurement framework describes an open procedure (works) for the renovation of the Sluisjesdijk (SLDK) sludge processing plant within the framework of Project Sluisjesdijk 2.0. The assignment focuses on an integrated, step-by-step renewal of the technical installations that are nearing the end of their service life, while maintaining the continuity of sludge processing during the works. The approach is based on a construction team model, involving a collaborative verification and design agency, with the possibility to outsource sub-processes to specialized contractors. The total value of the assignment is currently unknown, and the deadline has not been specified.

Slibverwerkingsbedrijf Sluisjesdijk (SLDK) was completed in 1986. SLDK processes sludge produced by RWZI Dokhaven and three other RWZI's. The technical installations at Sluisjesdijk are approaching the end of their service life. WSHD is looking for a contractor for the realization of the large-scale renovation of the Sluisjesdijk sludge processing plant, hereinafter also referred to as 'Project Sluisjesdijk 2.0' or 'Project SLDK2.0'. With the package of measures and investments, SLDK is to be made robust and future-proof again, utilizing realistic and pragmatic possibilities for sustainability

45252140Works
1Realisation Partner Sluisjesdijk 2.0€1

02Exclusion grounds

Exclusion grounds — consult the ESPD
  • No specific exclusion grounds were extracted. In a European tender, the mandatory and discretionary grounds of art. 2.86/2.87 of the Dutch Procurement Act almost always apply — check the European Single Procurement Document (ESPD).

03Value in context

Estimate not published

The contracting authority did not publish an estimated value — common for a large share of contracts. The EU threshold for werken is € 5,54 M, for reference.

04Likely competitors

#Likely bidderFitWins
1Heijmans Infra B.V.SME9365×
2Boskalis Nederland B.V.SME8969×
3KWS Infra B.V.SME8892×
4Dura Vermeer Infra Regionale Projecten BVSME8858×
5Van Gelder BVSME8853×
6BAM Infra B.V.SME8677×

05Legal themes that may be relevant here

06Frequently asked questions

What is the goal of Project Sluisjesdijk 2.0?
The goal is the large-scale renovation of the Sluisjesdijk (SLDK) sludge processing plant to make the technical installations, which are at the end of their service life, robust and future-proof again.
In what manner will the renovation of the installations be carried out?
The renovation takes place via an integrated, step-by-step, and modular approach in which sub-processes are renewed consecutively. In this, the aim is to maintain the continuity of sludge processing, whereby temporary installations will be placed where necessary.
What does the cooperation in the construction team look like?
In a construction team context, efforts will be made to reach a Final Design (DO) for each sub-process with the contractor based on a preliminary design+ (VO+). An engineering firm has already been contracted for the design of the VO+.
Will the assignment for all sub-processes be awarded to the realisation partner?
Although the majority of the sub-processes will be realized via the construction team with the realisation partner, the contracting authority retains the possibility to outsource certain sub-processes to specialized contractors or to design and award them outside of the construction team.
Which disciplines are part of the execution works?
The works consist mainly of mechanical, electrical & instrumentation (E&I-TA), and civil engineering works, supplemented by various other fields and disciplines.

Automatically compiled from the official tender data and documents.

07Estimated value versus the market

p25
€ 1,4 mln
median
€ 3,6 mln
p75
€ 9,1 mln
deze opdracht

Gegunde waarden in CPV 45 · werken n=3159