ClosedWorksEuropeanOnderhandeling zonder bekendmakingGreen

Realization Huis voor de Samenleving Municipality of Deurne (Unforeseen circumstances)

Gemeente Deurne · Onderhandeling zonder bekendmaking · 1 lots · 325540
Type
Works
45000000
Estimated value
Not published
To deadline
Ongoing
Knock-outs
n/a
exclusion grounds
Award basis
Best price-quality ratio
Assess manuallyconfidence low

The Municipality of Deurne has re-engaged the original contractor, who was contracted for lot 1 of the ‘Huis voor de Samenleving’ project in 2021, for additional building works. These extra works arose due to unforeseen circumstances, such as the planned insulation method for the roof being unfeasible, the existing walls failing to meet sound insulation standards, and the necessity of an alternative solution for the climate ceilings. Pursuant to article 2.163e AW 2012, these works may be negotiated without public announcement. The municipality expects the contractor to execute the extra works within the agreed frameworks, maintaining quality, safety, and applicable building regulations. The assignment is a work order without a new procurement process, aimed at adjusting the existing project to meet the functional and regulatory requirements.

Works · Onderhandeling zonder bekendmaking · European procedure

Sustainability countsEuropean
Contracting authority
Contract type
Works
Onderhandeling zonder bekendmaking
Estimated value
Estimate not published
Submission deadline
Ongoing
Scope
European
European procedure
Lots
1
1 lots
Main CPV code
Location
Netherlands
CharacteristicsCPV 45WorksEU tenderGreen / SPPunforeseen circumstancesroof insulationsound insulation

01What is being requested

The Municipality of Deurne has re-engaged the original contractor, who was contracted for lot 1 of the ‘Huis voor de Samenleving’ project in 2021, for additional building works. These extra works arose due to unforeseen circumstances, such as the planned insulation method for the roof being unfeasible, the existing walls failing to meet sound insulation standards, and the necessity of an alternative solution for the climate ceilings. Pursuant to article 2.163e AW 2012, these works may be negotiated without public announcement. The municipality expects the contractor to execute the extra works within the agreed frameworks, maintaining quality, safety, and applicable building regulations. The assignment is a work order without a new procurement process, aimed at adjusting the existing project to meet the functional and regulatory requirements.

The contractor contracted in 2021 for lot 1 Building works of the project Realization Huis voor de Samenleving in the Municipality of Deurne has been engaged to perform works resulting from unforeseen circumstances in accordance with article 2.163e AW 2012. This works were unforeseen due to: - extra works on the roof because the intended insulation method proved impossible; - extra works because sound insulation standards were not met due to the composition of existing walls; - a different solution instead of the prescribed climate ceilings.

45000000Works
1Realization Huis voor de Samenleving Municipality of Deurne (Unforeseen circumstances)

02Exclusion grounds

Exclusion grounds — consult the ESPD
  • No specific exclusion grounds were extracted. In a European tender, the mandatory and discretionary grounds of art. 2.86/2.87 of the Dutch Procurement Act almost always apply — check the European Single Procurement Document (ESPD).

03Value in context

Estimate not published

The contracting authority did not publish an estimated value — common for a large share of contracts. The EU threshold for werken is € 5,54 M, for reference.

04Likely competitors

#Likely bidderFitWins
1KWS Infra B.V.SME9592×
2Hegeman Bouw & Infra B.V.SME9531×
3Van Gelder BVSME9553×
4Combinatie Heijmans - SWARCOUnknown9473×
5BAM Bouw en Techniek bvSME9434×
6Heijmans Infra B.V.SME9465×

05Legal themes that may be relevant here

06Frequently asked questions

What is the reason for this assignment?
The assignment concerns building works that have become necessary due to unforeseen circumstances. This relates to the insulation method of the roof, the sound insulation standards of existing walls, and an alternative solution for the climate ceilings.
On what legal basis are these works being carried out?
The works are being carried out in accordance with article 2.163e AW 2012, because the assignment arises from unforeseen circumstances during the Realization Huis voor de Samenleving project.
Who is responsible for the execution of these extra works?
The contractor who was already contracted in 2021 for the building works of lot 1 of the Realization Huis voor de Samenleving project has been engaged for these additional works.

Automatically compiled from the official tender data and documents.

07Estimated value versus the market

p25
€ 1,4 mln
median
€ 3,6 mln
p75
€ 9,1 mln
deze opdracht

Gegunde waarden in CPV 45 · werken n=3159