AwardedWorksEuropeanOpenGreen

Framework Agreement: Maintenance of closed paving

Gemeente Ermelo · Open · 1 lots · 357444
Type
Works
45233222
Estimated value
€ 11M
awarded
To deadline
Ongoing
Knock-outs
n/a
exclusion grounds
Award basis
Best price-quality ratio
Assess manuallyconfidence low

The Municipality of Ermelo, acting as the lead municipality for the municipalities of Ermelo, Harderwijk, and Putten, is establishing a framework agreement for the maintenance of closed paving. The agreement enters into force on 1 April 2025 and has a basic duration of two years, with the possibility of two extensions of one year each. The work includes milling, filling, surface treatments, the application of asphalt and concrete paving, grass concrete blocks, verges, street works, and additional tasks. The tender is open and based on unit prices, whereby one framework contractor is responsible for the asphalting of roads on call. The focus is on ensuring a good condition of the paving and providing a flexible, cost-efficient solution for the three municipalities.

Works · Open · European procedure

Sustainability countsEuropean
Contracting authority
Contract type
Works
Open
Estimated value
€10,500,000
awarded value
Submission deadline
Ongoing
12:00
Scope
European
European procedure
Lots
1
1 lots
Main CPV code
Location
Netherlands
CharacteristicsCPV 45WorksEU tenderGreen / SPPpavingasphaltmaintenance

01What is being requested

The Municipality of Ermelo, acting as the lead municipality for the municipalities of Ermelo, Harderwijk, and Putten, is establishing a framework agreement for the maintenance of closed paving. The agreement enters into force on 1 April 2025 and has a basic duration of two years, with the possibility of two extensions of one year each. The work includes milling, filling, surface treatments, the application of asphalt and concrete paving, grass concrete blocks, verges, street works, and additional tasks. The tender is open and based on unit prices, whereby one framework contractor is responsible for the asphalting of roads on call. The focus is on ensuring a good condition of the paving and providing a flexible, cost-efficient solution for the three municipalities.

Contracting authority and lead municipality This tender is for the municipalities: Ermelo, Harderwijk, and Putten. The Municipality of Ermelo is the lead municipality. A new agreement as of 1 April 2025 for Maintenance of closed paving for a period of two (2) years with an option to extend twice for one (1) year each. In this context, closed paving refers to the asphalting of roads on call with one framework contractor based on unit prices. The work consists mainly of: a. milling of asphalt paving; b. filling of asphalt paving; c. application of surface treatment; d. application of as

45233222Works
1Framework Agreement: Maintenance of closed paving€7

02Outcome

Awarded

NTP B.V.

Award value
€10,500,000
Bidders
6

03Exclusion grounds

Exclusion grounds — consult the ESPD
  • No specific exclusion grounds were extracted. In a European tender, the mandatory and discretionary grounds of art. 2.86/2.87 of the Dutch Procurement Act almost always apply — check the European Single Procurement Document (ESPD).

04Value in context

Estimate not published

The contracting authority did not publish an estimated value — common for a large share of contracts. The EU threshold for werken is € 5,54 M, for reference.

05Bidders in this segment

#Likely bidderFitWins
1KWS Infra B.V.SME10092×
2BAM Infra B.V.SME10077×
3Van Gelder BVSME10053×
4D. van der Steen B.V.SME10031×
5Heijmans Infra B.V.SME10065×
6Dura Vermeer Infra Regionale Projecten BVSME10058×

06Legal themes that may be relevant here

07Frequently asked questions

For which municipalities is this framework agreement intended?
The agreement is for the municipalities of Ermelo, Harderwijk, and Putten, with the Municipality of Ermelo acting as the lead municipality.
What is the duration and structure of the agreement?
The agreement has a basic duration of two years and includes the possibility for two extensions of one year each.
What is the commencement date of the agreement?
The new agreement for the maintenance of closed paving enters into force on 1 April 2025.
Which activities fall under the scope of the agreement?
The work includes, among other things, the milling, filling, and application of asphalt and concrete paving, the application of surface treatments, grass concrete blocks/verge concrete, the replenishment of verges, and street works.
In what manner will the contract be executed?
It concerns the asphalting of roads on call with one framework contractor based on unit prices.

Automatically compiled from the official tender data and documents.

08Estimated value versus the market

p25
€ 1,4 mln
median
€ 3,6 mln
p75
€ 9,1 mln
€ 11 mln

Gegunde waarden in CPV 45 · werken n=3159