OpenWorksEuropeanOpen

Raising industrial estate Oosterhorn-zuid phase 3 Delfzijl

Groningen Seaports n.v. · Open · 409731
Type
Works
45100000-8 · Preparing land for con
Estimated value
Not published
To deadline
-64d
Apr 13, 2026 · 10:00
Knock-outs
n/a
exclusion grounds
Award basis
Best price-quality ratio
2 criteria
Assess manuallyconfidence high

This tender concerns the preparation for construction of approximately 80 hectares of industrial estate in Delfzijl via a construction team arrangement. The award takes place on the basis of the best price-quality ratio, where quality carries more weight than price.

Works · Open · European procedure

EuropeanComplete timeline
Contracting authority
Contract type
Works
Open
Estimated value
Estimate not published
Submission deadline
April 13, 2026
10:00
Scope
European
European procedure
Lots
Single contract
Main CPV code
Preparing land for construction
Location
Netherlands
CharacteristicsCPV 45WorksEU tenderEarthworksconstruction teamdesign

01What is being requested

The assignment concerns the elaboration of the Reference Design through to a Final Design in a construction team context and the subsequent preparation for construction of approximately 80 hectares of industrial area Oosterhorn-zuid phase 3 in Delfzijl. The works include the design phase, the realization phase (earthmoving, raising, watercourses) and supporting activities such as permit support and environmental management.

The works consist of, among others: /nA. Design phase (elaboration RO through DO) /nB. Realization phase (preparing site for construction) /nC. Supporting activities and responsibilities /nD. Specific points of attention and interfaces

45100000-8Works

02Strategic insight

Strategic insight · AI analysis
Focus strongly on the quality score, as this determines the largest part of the award with 70 points. Ensure an integral Quality Plan that provides insight into the approach to soil flows and the process during the construction team phase. Strictly observe the form requirements of the standard forms to prevent exclusion.
Read automatically from the tender documents using AI. Always verify against the original documents.

03Points of attention

Important · 6
Use of standard forms is mandatory; modification or addition leads to exclusion.Important
The validity period of the bid must be at least 90 calendar days after submission.Important
All communication and documents must be in the Dutch language.Important
Bids must be signed by an authorized representative in accordance with the Commercial Register.Important
Unambiguous consent must be given for the processing of personal data in accordance with GDPR.Important
Specific attention is required for compaction, control of settlements, administration of soil flows and the planning.Important

04Exclusion grounds

Exclusion grounds — consult the ESPD
  • No specific exclusion grounds were extracted. In a European tender, the mandatory and discretionary grounds of art. 2.86/2.87 of the Dutch Procurement Act almost always apply — check the European Single Procurement Document (ESPD).

05Award criteria

Award criterion B: Qualitymaximaal 70 punten

Assessment of the quality of the bid.

Award criterion A: Pricemaximaal 30 punten

Assessment of the price based on the submitted price information.

06Process & timeline

Information in case of justified commercial interest
28 januari t/m 17 februari 2026
Kick-off meeting at GSP office in Delfzijl
12 februari 2026
Final receipt of questions for 1st round of questions
23 februari 2026, 12.00 uur
Publication of Note of Information 1st round of questions
2 maart 2026
Final receipt of questions for 2nd round of questions
18 maart 2026, 12.00 uur
Publication of Note of Information 2nd round of questions
26 maart 2026
Final receipt of bids
13 april 2026, 10.00 uur
Opening of the tender box
13 april 2026, 10.30 uur
Publication of Tender Report
15 april 2026
Interviews
11 en 12 mei 2026?
Sending award decision
20 mei 2026
Stand-still period of at least 20 calendar days
21 mei t/m 10 juni 2026
Versturen definitieve gunning en afwijzing
Week 24-2026
Ingangsdatum van de werkzaamheden
Week 25
Bouwteamfase: Opdrachtverlening
Begin juni 2026
Bouwteamfase: Challenge SO en toprisico’s
Juni – augustus 2026
Bouwteamfase: Uitwerken VO, DO en werkplan
Augustus – oktober 2026
Bouwteamfase: Overeenkomen Realisatieovereenkomst
Oktober 2026
Realisatiefase: Werkvoorbereiding
November 2026 – begin 2027
Realisatiefase: Start Realisatie Bouwrijp maken terrein
Vanaf november 2026 t/m 2030

07Value in context

Estimate not published

The contracting authority did not publish an estimated value — common for a large share of contracts. The EU threshold for werken is € 5,54 M, for reference.

08Likely competitors

#Likely bidderFitWins
1Boskalis Nederland B.V.SME10069×
2KWS Infra B.V.SME9892×
3Heijmans Infra B.V.SME9665×
4Dura Vermeer Infra Regionale Projecten BVSME9558×
5Van Gelder BVSME9453×
6Fa. Gebr. Van der LeeUnknown9323×

09Tender documents

002-Bijlage 02 - Staat van ontledingpdfJan 27, 2026 · 136 KB
100-Bouwteamovereenkomst 1.0pdfJan 27, 2026 · 206 KB
302-Tekening nr. 51017701-DwarsprofielenpdfJan 27, 2026 · 625 KB
002-Bijlage 02 - Staat van OntledingxlsxJan 27, 2026 · 49 KB
208-Bijlage 10 - Beleid Socialreturn Groningen SeaportspdfJan 27, 2026 · 583 KB
211-Bijlage 13a - Over Better Performance - CROWpdfJan 27, 2026 · 137 KB
103-Appendix 3-Taakverdeling OG-ONpdfJan 27, 2026 · 39 KB
uea_560974_20260115140848pdfJan 27, 2026 · 335 KB
002 Bijlage B - UEA uea_560974_20260115140848pdfJan 27, 2026 · 335 KB
210-Bijlage 12 -Template omgevingsplandocxJan 27, 2026 · 83 KB
303-grondbalans Schetsontwerp overhoogte en depotspdfJan 27, 2026 · 88 KB
201-Bijlage 03 - Definitielijst ophogen bedrijventerrein Oosterhorn-zuid fase 3pdfJan 27, 2026 · 95 KB

10Legal themes that may be relevant here

11Frequently asked questions

What does the scope of the assignment entail?
The assignment includes the design phase (elaboration of RO through DO), the realization phase for preparing the site for construction, supporting activities and specific responsibilities regarding the interfaces.
What experience requirements must bidders meet?
Bidders must provide proof of experience in a full design phase (from RO through DO) and the realization of sites, as well as documented expertise in preparing land for construction.
Which suitability criteria are used for selection?
Characteristic experience in both design and site preparation projects on land and the capacity to operate within the digital procurement procedure will be considered.
In what manner is the assignment awarded?
The assignment is awarded on the basis of the best price-quality ratio.

Automatically compiled from the official tender data and documents.

12Estimated value versus the market

p25
€ 1,4 mln
median
€ 3,6 mln
p75
€ 9,1 mln
deze opdracht

Gegunde waarden in CPV 45 · werken n=3159