PlannedWorksMarktconsultatie

Hollandsekade Embankment Reinforcement

Hoogheemraadschap De Stichtse Rijnlanden · Marktconsultatie · 1 lots · 417574
Type
Works
45246200 · Bank protection works
Estimated value
Not published
To deadline
Ongoing
Knock-outs
n/a
exclusion grounds
Award basis
Best price-quality ratio
Assess manuallyconfidence moderate

Market consultation for the renovation of the Hollandsekade and an adjacent cycle path with a strict requirement for fully emission-free execution in a Natura 2000 area.

Works · Marktconsultatie · National procedure

Complete timeline
Contracting authority
Zuid-Holland
Contract type
Works
Marktconsultatie
Estimated value
Estimate not published
Submission deadline
Ongoing
Scope
National
National procedure
Lots
1
1 lots
Main CPV code
Bank protection works
Location
Nieuwkoop, Zuid-Holland
CharacteristicsCPV 45Worksembankment reinforcementcycle path reconstructionNatura 2000 area

01What is being requested

Realization of an embankment reinforcement and the reconstruction of a cycle path, consisting of the removal of 1,600 meters of revetment, the installation of steel sheet piles, and earthworks.

Hoogheemraadschap De Stichtse Rijnlanden will address the dike and the revetments along the Hollandse Kade. As a water board, we are responsible for the maintenance and management of the dike with the revetment. We are collaborating in this with the Municipality of Nieuwkoop, which is responsible for the maintenance of the adjacent cycle path. The section where we are working runs from the junction of the Milandweg and the Hollandsekade to the end of the cycle path at Hollandsekade 23. It is intended that HDSR organizes an oral (1-on-1) market consultation in preparation for a procurement for

45246200Works
1Hollandsekade Embankment Reinforcement

02Strategic insight

Strategic insight · AI analysis
Prepare yourself for the challenge of emission-free execution within the nitrogen-sensitive zone. Investigate the impact of the 25 kilometer radius on your logistics and equipment. Focus on the financial and practical consequences of the zero emission requirement for the procurement.
Read automatically from the tender documents using AI. Always verify against the original documents.

03Points of attention

Important · 5
Execution must be 100% emission-free.Important
Nitrogen deposition must be 0.0 mol/ha/yr.Important
The requirement applies to a radius of 25 kilometers around the project area.Important
The assignment is divided into two lots.Important
The contracting authority aims for one market party for both lots.Important

04Process & timeline

Publication of market consultation documents
26 maart 2026
Submitting questions
2 april 2026
Registration for market consultation
8 april 2026
Confirmation of registration and time slot
9 april 2026
Market consultation interview rounds
13, 15 en 16 april 2026
Publication of final market consultation report
12 mei 2026
Publication of EU procurement
medio december 2026
Award of works
medio mei 2027
Project preparation
mei t/m augustus 2027
Execution period of outdoor works
september 2027 t/m februari 2028

05Value in context

Estimate not published

The contracting authority did not publish an estimated value — common for a large share of contracts. The EU threshold for werken is € 5,54 M, for reference.

06Likely competitors

#Likely bidderFitWins
1KWS Infra B.V.SME10092×
2Boskalis Nederland B.V.SME10069×
3Dura Vermeer Infra Regionale Projecten BVSME10058×
4BAM Infra B.V.SME9977×
5Heijmans Infra B.V.SME9965×
6ENGIE Infra & Mobility B.V.SME9969×

07Tender documents

#2089138-v2-422302-RWK - Bijlage 1 bij Marktconsultatie 422 HollandsekadepdfMar 26, 2026 · 4187 KB
TN576091 - EFE1 Vrijwillige aankondiging van voorafgaande marktconsultatie 20260326130832pdfMar 26, 2026 · 178 KB
#2089136-v2-422302-RWK - Marktconsultatiedocument 422302 HollandsekadepdfMar 26, 2026 · 300 KB

08Legal themes that may be relevant here

09Estimated value versus the market

p25
€ 1,4 mln
median
€ 3,6 mln
p75
€ 9,1 mln
deze opdracht

Gegunde waarden in CPV 45 · werken n=3159