Area North - Renovating E and W Installations Bridge Noord Willemskanaal D-003298
Renovation of the electrical and mechanical installations of the bridge Noord Willemskanaal in Groningen.
Works · Restricted · National procedure
01What is being requested
The work concerns the renovation of the electrical and mechanical installations of the bridge Noord Willemskanaal, including security, bridge works, and electrotechnical works.
The work involves the renovation of the existing electrical and mechanical installations and mainly consists of: (newline) (newline)Security: (newline)Relocating the key interlocking cabinet from the bridge post to the street cabinet, including replacing the cables between the bridge control installation/key interlocking cabinet and the relay house. (newline) (newline)Bridge works: (newline)Performing design and detailing work, replacing and revising various parts of the bridge movement mechanism, replacing the main and emergency drives, balancing the bridge fall, and installing safety featur
02Outcome
Machinefabriek Rusthoven B.V.
03Strategic insight
Focus on a high CO2 ambition level to achieve the maximum fictitious discount percentage. Ensure an accurate substantiation of the bid amount in the budget.
04Points of attention
05Award criteria
Quality value is calculated based on the indicated CO2 ambition level (step 1 through 5), resulting in a fictitious discount percentage on the bid amount.
The best price-quality ratio is determined by the lowest evaluation price, whereby the bid amount is reduced by a fictitious discount based on the CO2 Prestatieladder.
06Value in context
The contracting authority did not publish an estimated value — common for a large share of contracts. The EU threshold for werken is € 5,54 M, for reference.
07Bidders in this segment
08Tender documents
09Legal themes that may be relevant here
10Frequently asked questions
Which specific bridge is involved in this assignment?
What is the exact scope of the works for the installations?
What works are being carried out on the bridge movement mechanism?
How is the validity period of the selection criteria handled?
Automatically compiled from the official tender data and documents.
11Estimated value versus the market
€ 1,4 mln
€ 3,6 mln
€ 9,1 mln
Gegunde waarden in CPV 45 · werken n=3159