AwardedWorksEuropeanOpenGreen

EU public procurement for Construction Team Pumping Station and Revetment Kromme Rijn

Type
Works
45200000
Estimated value
€ 9,00M
estimated
To deadline
Ongoing
Knock-outs
n/a
exclusion grounds
Award basis
Best price-quality ratio
Assess manuallyconfidence moderate

This document contains the general terms and conditions UAV 2012 for the execution of works and technical installation works. It regulates the rights and obligations of both the contracting authority and the contractor.

Works · Open · European procedure

Sustainability countsEuropean
Contract type
Works
Open
Estimated value
€9,000,000
estimated value
Submission deadline
Ongoing
09:00
Scope
European
European procedure
Lots
1
1 lots
Main CPV code
Location
Netherlands
CharacteristicsCPV 45WorksEU tenderGreen / SPP

01What is being requested

The assignment concerns the execution of works and technical installation works in accordance with the provisions in the agreement and the UAV 2012.

EU procurement for the purpose of contracting one Contractor (whether or not in combination) to work intensively in a construction team relationship with the Contracting Authority to arrive at a supported design, specification/work description (UAV), risk allocation, and construction sum for a new pumping station with revetment to be built for the purpose of water supply to the Kromme Rijn (phase 1). If both parties agree, the 2nd phase, the realization of the works, will be awarded. The assignment concerns a one-time assignment.

45200000€ 9,00MWorks
1Pumping Station and Revetment Kromme Rijn€9,000,000

02Strategic insight

Strategic insight · AI analysis
Ensure strict compliance with the UAV 2012 conditions during the execution of the works. Take into account the liability for damage to the contracting authority's property due to negligence. Ensure that all subcontractors are fully informed about the relevant specification provisions.
Read automatically from the tender documents using AI. Always verify against the original documents.

03Points of attention

Important · 5
The contractor is obliged to repair or renew insufficient work within a period to be set by the management.Important
The contractor must grant the management free access to the sites and workshops for inspection.Important
In the case of subcontracting, prior written approval from the management is required.Important
The contractor is jointly and severally liable if two or more persons have jointly accepted the work.Important
The contractor must warn the management in case of apparent contradictions between parts of the specification.Important

04Exclusion grounds

Exclusion grounds — consult the ESPD
  • No specific exclusion grounds were extracted. In a European tender, the mandatory and discretionary grounds of art. 2.86/2.87 of the Dutch Procurement Act almost always apply — check the European Single Procurement Document (ESPD).

05Value in context

€9,000,000

06Bidders in this segment

#Likely bidderFitWins
1ENGIE Infra & Mobility B.V.SME9869×
2KWS Infra B.V.SME9892×
3BAM Infra B.V.SME9877×
4Heijmans Infra B.V.SME9865×
5Dura Vermeer Infra Regionale Projecten BVSME9758×
6Ploegam B.V.SME9722×

07Tender documents

TN469359 - EF29 Aankondiging gegunde opdracht - algemene richtlijn, standaardregeling 20241205094202pdfDec 6, 2024 · 10 KB
Nota van inlichtingen 2024-09-16-1pdfSep 16, 2024 · 31 KB
Bijlage K - Quickscan_Wnb_2023_HDSR_Inlaat_Kromme_Rijn_WbD_V3 definitief 21 maart 2024pdfSep 16, 2024 · 2679 KB
GKR, Inschrijvingsleidraad, Bijlage 11 Concept bouwteamovereenkomst_Gemaal_Kromme_Rijn 3.0 - gepubliceerd bij NvI 2024-09-16-1docxSep 16, 2024 · 93 KB
GKR, Inschrijvingsleidraad 3.0 - gepubliceerd bij NvI 2024-09-16-1pdfSep 16, 2024 · 1284 KB
Nota van inlichtingen 2024-09-05-1pdfSep 5, 2024 · 12 KB
Nota van inlichtingen 2024-07-22-1pdfJul 22, 2024 · 6 KB
GKR, Inschrijvingsleidraad, Bijlage J SSK Deelraming Alternatief 1 VKApdfJul 17, 2024 · 370 KB
GKR, Inschrijvingsleidraad, Bijlage 12 Beoordelingsmatrix (versie 2)xlsJul 17, 2024 · 56 KB
TN469359 - EF16 Aankondiging van een opdracht - algemene richtlijn, standaardregeling 20240717175648pdfJul 17, 2024 · 14 KB
GKR, Inschrijvingsleidraad, Bijlage 09 Inschrijfstaat (versie 03)xlsxJul 17, 2024 · 27 KB
Nota van inlichtingen 2024-07-17-1pdfJul 17, 2024 · 15 KB

08Legal themes that may be relevant here

09Frequently asked questions

What is the specific setup of the assignment for the pumping station and revetment?
The assignment is contracted in a construction team relationship. Phase 1 consists of intensive collaboration with the contracting authority to arrive at a design, specification/work description (UAV), risk allocation, and construction sum. Upon mutual agreement, phase 2 follows, the realization of the works.
Which general terms and conditions apply to the execution of the works?
The execution of the works and technical installation works takes place on the basis of the Uniform Administrative Conditions for the execution of works and technical installation works 2012 (UAV 2012).
What is the goal of the construction team assignment at the Kromme Rijn?
The goal is the realization of a new pumping station with revetment to be built for the purpose of water supply to the Kromme Rijn.

Automatically compiled from the official tender data and documents.

10Estimated value versus the market

p25
€ 1,4 mln
median
€ 3,6 mln
p75
€ 9,1 mln
€ 9,0 mln

Gegunde waarden in CPV 45 · werken n=3159