Almere-Lelystad Through-Cycling Route
This project concerns the realization of the through-cycling route between Almere and Lelystad by means of various civil engineering works. The execution is divided into four specific routes with various deadlines in 2025 and 2026.
Works · Open · European procedure
01What is being requested
Realization of the Almere-Lelystad Through-Cycling Route consisting of four routes. The assignment includes, among other things, earthworks, the application of various pavings, grounds maintenance, and the installation of public lighting.
It concerns a through-cycling route of min. 4.00 meters wide that is equipped with lighting. The entire through-cycling route starts at the Buitenring at the connection Gerard Monninckpad/ Kotterbosweg (Almere) and ends at the level of the connection to the Knardijk. The length concerns approx. 10.1 kilometers. The through-cycling route is realized in a settlement-sensitive area, where limited workspace is available. The Contracting Authority sees challenges for the Contractor in creating sufficient storage possibilities for material and equipment and organizing the construction logistics, giv
02Outcome
Fa. Gebr. Van der Lee
03Strategic insight
Ensure precise coordination with Staatsbosbeheer for the layout of depots. Take into account strict ecological restrictions and working hours to prevent delays. A good Better Performance score is essential for future assignments.
04Points of attention
05Exclusion grounds
- No specific exclusion grounds were extracted. In a European tender, the mandatory and discretionary grounds of art. 2.86/2.87 of the Dutch Procurement Act almost always apply — check the European Single Procurement Document (ESPD).
06Process & timeline
07Value in context
The contracting authority did not publish an estimated value — common for a large share of contracts. The EU threshold for werken is € 5,54 M, for reference.
08Bidders in this segment
09Tender documents
10Legal themes that may be relevant here
11Frequently asked questions
What are the technical specifications of the through-cycling route to be realized?
What logistical challenges are there during the execution of the works?
May a framework agreement be used to meet the technical suitability requirement for concrete cycle paths?
Which works are among others carried out at the Kotterbosweg?
Automatically compiled from the official tender data and documents.
12Estimated value versus the market
€ 1,4 mln
€ 3,6 mln
€ 9,1 mln
Gegunde waarden in CPV 45 · werken n=3159