AwardedSuppliesEuropeanOpen

Centrifuges SVI Mierlo

Waterschap De Dommel · Open · 1 lots · 337422
Type
Supplies
42996000
Estimated value
€ 2,79M
awarded
To deadline
Ongoing
Knock-outs
1
exclusion grounds
Award basis
Best price-quality ratio
3 criteria
Assess manuallyconfidence high

This European procurement concerns the supply and maintenance of four dewatering centrifuges for Waterschap De Dommel at the SVI Mierlo location for a period of 15 years.

Supplies · Open · European procedure

European1 exclusion groundsComplete timeline
Contracting authority
Contract type
Supplies
Open
Estimated value
€2,787,076
awarded value
Submission deadline
Ongoing
09:00
Scope
European
European procedure
Lots
1
1 lots
Main CPV code
Location
Netherlands
CharacteristicsCPV 42SuppliesEU tender

01What is being requested

The design, manufacture, delivery, assembly, and commissioning of four dewatering centrifuges at the SVI Mierlo, including a guarantee period of 1 year and maintenance for 15 years.

The work concerns the design, drawing, manufacturing, delivery, transport, assembly, testing, and commissioning of four dewatering centrifuges at the Slibverwerkingsinstallatie (SVI) Mierlo. This contract also includes the provision of a guarantee during a guarantee period of 1 year and maintenance for a period of 15 years.

42996000Supplies
1Centrifuges SVI Mierlo

02Outcome

Awarded

GEA Westfalia Separator Nederland B.V.

Award value
€2,787,076
Bidders
4

03Strategic insight

Strategic insight · AI analysis
Ensure a complete TCO table and a detailed machine description to prevent exclusion. Check whether the maintenance agreement complies exactly with the stated requirements regarding the termination clause. In the case of a partnership, pay attention to strict compliance with competition rules.
Read automatically from the tender documents using AI. Always verify against the original documents.

04Points of attention

Important · 5
It is not permitted to submit a bid more than once.Important
Bidders sign as main contractor for joint and several liability.Important
The maintenance agreement must contain a termination clause with specific terms.Important
All documents must be drafted in the Dutch language.Important
Documents requiring signature must be legally signed by authorized persons.Important

05Can I take part?

Technical — References must meet the requested core competencies.
Exclusion ground — No application of exclusion grounds to the organization.

06Exclusion grounds

Exclusion grounds (1)
  • No application of exclusion grounds to the organization.

07Award criteria

qualitative award criteriaweight n/a

Detailed qualitative award criteria must be submitted.

Total cost of ownership (TCO)weight n/a

To be completed via the TCO Table Centrifuges SVI Mierlo.

price-quality ratioweight n/a

The assessment takes place based on the best price-quality ratio, whereby in the event of equal scores, the lowest fictitious bid or the highest total quality value shall be decisive.

08Process & timeline

Publication TenderNed
24-05-2024
Site inspection
1[telefoonnummer verwijderd]:00 – 14:00
Closing period for submitting questions
17-06-2024 10:00
Availability of Notice of Clarification
20-06-2024
Deadline for submitting bids
[telefoonnummer verwijderd]:00
Opportunity for verification interview
10-07-2024 t/m 12-07-2024
Expected date of notification of award decision
12-07-2024
Sending final award
02-08-2024

09Value in context

Estimate not published

The contracting authority did not publish an estimated value — common for a large share of contracts. The EU threshold for leveringen is € 221.000, for reference.

10Bidders in this segment

#Likely bidderFitWins
1Sulzer Pumps Wastewater Netherlands B.V.SME9062×
2Kurstjens B.V.SME67
3GEA Westfalia Separator Nederland B.V.SME67
4Xylem Water Solutions Nederland B.V.SME63
5Distrimex Pompen & Service B.V.SME63
6Service in Separation B.V.SME62

11Tender documents

TN468219 - EF29 Aankondiging gegunde opdracht - algemene richtlijn, standaardregeling 20240820105411pdfAug 21, 2024 · 9 KB
Nota van inlichtingen 2024-07-01-1pdfJul 1, 2024 · 2 KB
Concept realisatieovereenkomst Waterschap De Dommel 20-06-2024docJun 20, 2024 · 151 KB
Nota van inlichtingen 2024-06-20-4pdfJun 20, 2024 · 60 KB
ref 97 - ZSV000007-13- -0008_27-1 Centrifuge incl scopepdfJun 20, 2024 · 95 KB
Proces verbaal van aanwijzing Centrifuges SVI MierlopdfJun 20, 2024 · 40 KB
Tekeningen Ref. 12zipJun 20, 2024 · 897 KB
Concept co��rdinatieovereenkomst Waterschap De Dommel 20-06-2024docxJun 20, 2024 · 48 KB
Tekeningen CentrifugeszipJun 5, 2024 · 774 KB
P084701-SVI-RAP-DF-PT-A16 Bestek Centrifuges SVI MierlopdfMay 26, 2024 · 1382 KB
Concept realisatieovereenkomst Waterschap De Dommel(31153140)pdfMay 26, 2024 · 157 KB
AWVODI-2018pdfMay 26, 2024 · 379 KB

12Legal themes that may be relevant here

13Frequently asked questions

What exactly does the contract for the centrifuges SVI Mierlo entail?
The contract includes the design, drawing, manufacturing, delivery, transport, assembly, testing, and commissioning of four dewatering centrifuges at the Slibverwerkingsinstallatie (SVI) Mierlo.
What is the duration of the guarantee and the maintenance?
The contract includes the provision of a guarantee during a guarantee period of 1 year and maintenance for a period of 15 years.
Which phases are distinguished in the execution of the work?
The work is divided into the design phase, the realization phase, the testing phase, and the commissioning phase.

Automatically compiled from the official tender data and documents.

14Estimated value versus the market

p25
€ 300K
median
€ 800K
p75
€ 4,0 mln
deze opdracht

Gegunde waarden in CPV 42 · leveringen n=273