OpenWorksEuropeanOpen

Flanking measures Network Analysis

Gemeente Tilburg · Open · 1 lots · 427799
Type
Works
45233120 · Civil engineering work
Estimated value
Not published
To deadline
35d
Jul 21, 2026 · 08:00
Knock-outs
3
exclusion grounds
Award basis
Best price-quality ratio
2 criteria
Caution — high thresholdconfidence high

This EU procurement concerns the realization of various road reconstructions in Tilburg as flanking measures for the Ringbaan West. It concerns a framework agreement for eight sub-projects with an estimated value of up to € 9 million.

Works · Open · European procedure

European3 exclusion groundsComplete timeline
Contracting authority
Gemeente Tilburg
Noord-Brabant
Contract type
Works
Open
Estimated value
Estimate not published
Submission deadline
July 21, 2026
08:00
Scope
European
European procedure
Lots
1
1 lots
Main CPV code
Civil engineering works
Location
Tilburg, Noord-Brabant
CharacteristicsCPV 45WorksEU tenderroad reconstructionstraffic measurescivil engineering

01What is being requested

Realization of 8 sub-projects for various road reconstructions as flanking traffic measures in Tilburg. The assignment concerns a framework agreement for works with an estimated value between € 7,000,000 and € 9,000,000.

The assignment that the Contracting Authority wishes to place on the market through this tender oversees the realization of various road reconstructions, serving as flanking traffic measures for the intended narrowing of the Ringbaan West traffic artery in Tilburg. These flanking measures must therefore be realized by July 1, 2028, at the latest. In the context of maintaining the accessibility of Tilburg, adjustments must be made to the road network in Tilburg at various locations. By assigning the various traffic measures to a single Contractor, the client sees significant advantages in term

45233120Works
1Flanking measures Network Analysis

02Strategic insight

Strategic insight · AI analysis
Ensure full and legally valid signing of all formats to avoid exclusion. Check the Gedragsverklaring Aanbesteden and the fiscal statement in good time due to the required processing time. Focus on the partnership that the municipality is seeking for the phasing of the sub-projects.
Read automatically from the tender documents using AI. Always verify against the original documents.

03Points of attention

Important · 4
Bidders must strictly adhere to the formats of the tender documents to prevent exclusion.Important
Questions must be submitted anonymized via the TenderNed question module.Important
The standstill period is two months after the tender deadline.Important
The assignment may be extended with additional works up to a maximum of € 1,500,000.Important

04Can I take part?

Financial · 1
Financial and economic capacity in accordance with the requirements stated in the reference sheet.Financial
Technical · 1
Technical ability and professional competence in accordance with the requirements stated in the reference sheet, including experience requirements and core competence in reference assignments.Technical
Exclusion ground · 3
No application of mandatory grounds for exclusion from Article 2.86 of the Aanbestedingswet 2012 in the 5 years prior to the closing of the tender period.Exclusion ground
No application of optional grounds for exclusion such as violation of environmental, social, or labor law, bankruptcy, serious professional misconduct, distortion of competition, conflict of interest, involvement in preparation, past performance, false declaration, or unlawful influence in the 3 years prior to the closing of the tender period.Exclusion ground
Declaration of no Russian involvement in accordance with the European regulation.Exclusion ground

05Exclusion grounds

Exclusion grounds (3)
  • No application of mandatory grounds for exclusion from Article 2.86 of the Aanbestedingswet 2012 in the 5 years prior to the closing of the tender period.
  • No application of optional grounds for exclusion such as violation of environmental, social, or labor law, bankruptcy, serious professional misconduct, distortion of competition, conflict of interest, involvement in preparation, past performance, false declaration, or unlawful influence in the 3 years prior to the closing of the tender period.
  • Declaration of no Russian involvement in accordance with the European regulation.

06Award criteria

Qualityweight n/a

Quality sub-criterion as part of the most economically advantageous tender.

Priceweight n/a

Price sub-criterion as part of the most economically advantageous tender.

07Process & timeline

Publication of Tender Documents
02-06-2026
Deadline for submitting questions
17-06-2026 10:00 uur
Publication of Note of Clarification
26-06-2026
Closing of tender period
21-07-2026 10:00 uur
Opening of digital vault
21-07-2026 10:01 uur
Award decision (provisional)
17-08-2026
Standstill period
20 dagen
Signing Agreement/final award
07-09-2026
Effective date Agreement/Start Assignment
15-09-2026
Final completion date
30-06-2028

08Value in context

Estimate not published

The contracting authority did not publish an estimated value — common for a large share of contracts. The EU threshold for werken is € 5,54 M, for reference.

09Likely competitors

#Likely bidderFitWins
1KWS Infra B.V.SME9992×
2Dura Vermeer Infra Regionale Projecten BVSME9958×
3D. van der Steen B.V.SME9931×
4ENGIE Infra & Mobility B.V.SME9969×
5BAM Infra B.V.SME9877×
6Combinatie Heijmans - SWARCOUnknown9873×

10Tender documents

Bijlage 1 - Juridische bepalingen Aanbestedingsprocedures Gemeente Tilburg (februari 2026)pdfJun 5, 2026 · 637 KB
Bijlage 9 - Uniform Europees Aanbestedingsdocument (UEA)pdfJun 5, 2026 · 577 KB
Aanbestedingsdocument Flankerende maatregelenpdfJun 5, 2026 · 943 KB
Bijlage 5 - Verplichting Wet basisregistratie ondergrondpdfJun 5, 2026 · 268 KB
Bijlage 7 - Referentieblad GeschiktheidseisdocxJun 5, 2026 · 50 KB
Bijlage 4 - UAV 2012 versie 2025pdfJun 5, 2026 · 1772 KB
Bijlage 2 - Bestek inclusief bijlagenzipJun 5, 2026 · 272292 KB
Bijlage 8 - InschrijvingsbiljetdocxJun 5, 2026 · 43 KB
Bijlage 3 - Omschrijving StelpostenpdfJun 5, 2026 · 278 KB
Bijlage 6 - Invulling verplichting Social Return on InvestmentpdfJun 5, 2026 · 323 KB
Bijlage 10 - Verklaring van geen-Russische betrokkenheiddocxJun 5, 2026 · 44 KB
TN593966 - EF16 Aankondiging van een opdracht - algemene richtlijn, standaardregeling 20260604095013pdfJun 5, 2026 · 212 KB

11Legal themes that may be relevant here

12Frequently asked questions

What is the objective of the assignment?
The assignment concerns the realization of various road reconstructions as flanking traffic measures for the intended narrowing of the Ringbaan West in Tilburg.
When must the works be completed?
The flanking measures must be realized by July 1, 2028, at the latest.
Which contract conditions apply to the execution?
The execution of the works takes place under the UAV 2012 (version 2025).
What is the composition of the assignment?
The main assignment for the flanking measures Network Analysis comprises 8 different sub-projects.

Automatically compiled from the official tender data and documents.

13Estimated value versus the market

p25
€ 1,4 mln
median
€ 3,6 mln
p75
€ 9,1 mln
deze opdracht

Gegunde waarden in CPV 45 · werken n=3159