AwardedSuppliesEuropeanOpen
33kV - 13kV 25MVA Transformers
N.V. Nederlandse Gasunie · Open · 1 lots · 368040
5
5 of 6 core insights found
Measures presence, not accuracy · documents remain authoritative
ScopeAdvicePoints of attentionSuitability requirementsAward criteriaTimeline
Type
Supplies
31210000
Estimated value
€ 5,00M
estimated
To deadline
Ongoing
Knock-outs
n/a
exclusion grounds
Award basis
Best price-quality ratio
2 criteria
Assess manuallyconfidence high
Gasunie is looking for a supplier for the delivery of a maximum of five 25MVA transformers with an estimated value of € 5 million.
Supplies · Open · European procedure
EuropeanComplete timeline
CharacteristicsCPV 31SuppliesEU tender
01What is being requested
Delivery of a maximum of five 25MVA transformers for a period of 48 months, with the option for an extension of 4 years.
Through this tender procedure, Gasunie aims to select one contractor for the delivery up to five (5) 25MVA transformer of the contract. The exact amount depends on the amount of H2 compressor systems to be procured which on its turn depends on the number of caverns to be filled with hydrogen.
133kV - 13kV 25MVA Transformers€5,000,000
02Outcome
Awarded
Sadinter S.A.
Award value
€5,000,000
vs. estimate
0%
Bidders
3
03Strategic insight
Strategic insight · AI analysis
When preparing the bid, focus strongly on quality as this carries the most weight. Ensure sharp pricing to maximize the 40 points. Take into account the framework agreement structure of the assignment.
04Points of attention
Important · 3
The exact quantity depends on the H2 compressor systems.Important
The bid must be submitted in English.Important
Electronic invoicing is used.Important
05Exclusion grounds
Exclusion grounds — consult the ESPD
- No specific exclusion grounds were extracted. In a European tender, the mandatory and discretionary grounds of art. 2.86/2.87 of the Dutch Procurement Act almost always apply — check the European Single Procurement Document (ESPD).
06Award criteria
Quality60
Assessment based on quality.
Price40
Assessment based on price.
07Process & timeline
Deadline for requesting additional information
24/03/2025 10:00 +01:00
Deadline for receiving bids
07/04/2025 10:00 +02:00
Opening
07/04/2025 10:00 +02:00
08Value in context
€5,000,000
09Bidders in this segment
#Likely bidderFitWins
1Hitachi Energy The Netherlands BVSME766×
2GE Nederland B.V.SME724×
3Sadinter S.A.Unknown711×
4Eaton Industries NLUnknown671×
5EFACEC Energia – Máquinas e Equipamentos Eléctricos, S.A.Unknown661×
6EKB Groep Noord B.V.SME641×
10Tender documents
TN512289 - EF17 Aankondiging van een opdracht - sectorale richtlijn, standaardregeling 20250217174138pdfFeb 19, 2025 · 8 KB
11Legal themes that may be relevant here
Advies 264> Aanbesteding van keuring en inspectie van elektrotechnische installaties. Klager heeft er op gewezen dat in de invulbijlage waarAdvies 649> Ondernemer klaagt erover dat de betrokken Europese openbare aanbesteding zowel ziet op het leveren van elektriciteit als het verComplaint upheldAdvies 611> Een Europese openbare aanbestedingsprocedure voor de renovatie van een rioolwaterzuiveringsinstallatie is beëindigd en aanbestedAdvies 440> Meervoudig onderhandse aanbestedingsprocedure voor een (concessie)opdracht voor diensten voor het beschikbaar stellen, plaatsen,Advies 300> Openbare Europese aanbesteding voor beheer en onderhoud van applicaties en aanverwante ICT-diensten. De zittende leverancier heeComplaint upheld
12Frequently asked questions
Are there possibilities for contract extension?
The assignment includes the option for one contract extension of 4 years.
What is the exact scope of the delivery?
It concerns the delivery of a maximum of five (5) 25MVA transformers (33kV - 13kV). The exact quantity depends on the quantity of H2 compressor systems being purchased, which in turn depends on the number of caverns to be filled with hydrogen.
Automatically compiled from the official tender data and documents.
13Estimated value versus the market
p25
€ 260K
€ 260K
median
€ 526K
€ 526K
p75
€ 1,4 mln
€ 1,4 mln
€ 5,0 mln
Gegunde waarden in CPV 31 · leveringen n=168