31187282: Major maintenance A2 and A6 (2025, 2026)

Rijkswaterstaat Programma's, Projecten en Onderhoud · Competitive dialogue · 2 lots · 356725
Type
Works
45233139
Estimated value
€ 24M
awarded
To deadline
Ongoing
Knock-outs
0
exclusion grounds
Award basis
Best price-quality ratio
Assess manuallyconfidence high

This tender concerns the engineering and execution of major maintenance on the A2 and A6 in Central Netherlands for the years 2025 and 2026. The contract is divided into two separate lots and is carried out via a competitive dialogue.

Works · Competitive dialogue · European procedure · SME-friendly

SME-friendlyEuropeanComplete timeline
Contract type
Works
Competitive dialogue
Estimated value
€23,757,000
awarded value
Submission deadline
Ongoing
15:00
Scope
European
European procedure
Lots
2
2 lots
Main CPV code
Location
Netherlands
CharacteristicsCPV 45WorksSME-friendlyEU tenderMajor maintenanceA2A6

01What is being requested

Contract for the engineering and execution of major maintenance on the A2 and A6 in Central Netherlands during 2025 and 2026. The works include, among other things, the superstructure, structures, gutters, catch basins, verges, vehicle barriers, and signage.

This project concerns Major Maintenance on the A2 and the A6 in 2025 and 2026. This is being placed on the market via a competitive dialogue light with two lots: lot A2 (case number 31187282) and lot A6 (case number 31203014). The project mainly includes maintenance of the asphalt (replacing the surface course and, where necessary, repairing the binder course) in addition to maintenance of structures and other objects such as vehicle barriers. The project is characterized by many repetitive works. An exception to this is the widening of connection curve R at Knooppunt Oudenrijn (lot A2) and t

45233139Works
131187282: Major maintenance A2 (2025, 2026)
231203014: Major maintenance A6 (2025, 2026)

02Outcome

Awarded

Heijmans Infra B.V.

Award value
€23,757,000
Bidders
3

03Breakdown by lot

31187282: Major maintenance A2 (2025, 2026)n/a
31203014: Major maintenance A6 (2025, 2026)n/a

Per-lot values not published — bars show only the lot breakdown.

04Strategic insight

Strategic insight · AI analysis
Prepare separate applications and bids for both lots. Ensure that the technical competence for surface course replacement and traffic systems is demonstrated with the correct lengths and categories. Focus on the project management experience that meets the specific financial thresholds per lot.
Read automatically from the tender documents using AI. Always verify against the original documents.

05Points of attention

Important · 4
The contract is executed via an engineering & construct contract under UAV-GC 2005.Important
There is no possibility to combine the two lots during bidding.Important
Works must be performed based on a certified quality management system in accordance with NEN-EN-ISO 9001.Important
For certain parts, such as connection curve R and the culverts, specific design obligations apply (VO, DO, and UO).Important

06Can I take part?

Technical · 3
In the five-year period preceding the deadline for receipt of requests to participate, having executed at least one contract in the construction sector (civil engineering, building & utilities, installation technology) with an agreed amount (contract sum) or invoiced amount equal to or greater than € 10,000,000 for Lot A2 and € 20,000,000 for Lot A6, where the entrepreneur was responsible for the dailyTechnical
In the five-year period preceding the deadline for receipt of requests to participate, having gained experience in the engineering and execution of carriageway-width surface course replacement with a continuous length of at least 2.5 km on a motorway with at least two lanes in the same direction.Technical
In the five-year period preceding the deadline for receipt of requests to participate, having gained experience in the execution of a traffic system on a motorway where Hindercategorie A* was applicable.Technical

07Exclusion grounds

Exclusion grounds — consult the ESPD
  • No specific exclusion grounds were extracted. In a European tender, the mandatory and discretionary grounds of art. 2.86/2.87 of the Dutch Procurement Act almost always apply — check the European Single Procurement Document (ESPD).

08Process & timeline

Announcement publication
8 november 2024
Information meeting Application phase
18 november 2024
Deadline for submission of requests for further information
27 november 2024
Publication of memorandum of information application phase
4 december 2024
Deadline for receipt of requests to participate
11 december 2024
Opening digital vault of requests to participate
12 december 2024
Sending notification of selection decision
20 december 2024
Deadline for complaint regarding selection decision
13 januari 2024
Sending invitation to information meeting dialogue
14 januari 2025
Information meeting Dialogue phase
15 januari 2025
Deadline for submission of request for further information
29 januari 2025
Providing/publication of memorandum of information
7 februari 2025
Uiterste datum indiening trechteringproduct
21 februari 2025
Verzenden trechteringbeslissing
4 maart 2025
Uiterste datum klacht trechteringbeslissing
14 maart 2025
Verzenden uitnodiging tot dialooggesprekken
17 maart 2025
Dialooggesprekken tweede fase dialoog
Week 13 + 14 2025
Uiterste datum indiening verzoek om nadere inlichtingen
15 april 2025
Verstrekken/publicatie nota van inlichtingen
25 april 2025
Afsluiten dialoog
25 april 2025

09Value in context

Estimate not published

The contracting authority did not publish an estimated value — common for a large share of contracts. The EU threshold for werken is € 5,54 M, for reference.

10Bidders in this segment

#Likely bidderFitWins
1KWS Infra B.V.SME10092×
2BAM Infra B.V.SME10077×
3Combinatie Heijmans - SWARCOUnknown10073×
4Heijmans Infra B.V.SME10065×
5Boskalis Nederland B.V.SME10069×
6Dura Vermeer Infra Regionale Projecten BVSME10058×

11Tender documents

TN495997 - EF29 Aankondiging gegunde opdracht - algemene richtlijn, standaardregeling 20251027161928pdfOct 29, 2025 · 15 KB
1e NvI met bijlagenzipDec 3, 2024 · 2099 KB
Presentatie Inlichtingenbijeenkomst Aanmeldfase - Groot Onderhoud MN A2 en A6 (2025 - 2026)pdfNov 19, 2024 · 1616 KB
Verslag Inlichtingenbijeenkomst Aanmeldfase - Groot Onderhoud MN A2 en A6 (2025 - 2026)pdfNov 19, 2024 · 84 KB
RTD 1007-4, versie 2.0 flexibele voegovergangsystemen, definitiefpdfNov 10, 2024 · 3554 KB
Projectspecifieke Bijlage 'Specificaties Profielverbetering A2'pdfNov 10, 2024 · 13 KB
Bijlage K Format Concept staat van ontleding van de MKI-waarde GO A6 ZaakID 31203014docxNov 10, 2024 · 42 KB
Bijlage D Model indieningsformulier GO perceel A6 ZaakID 31203014docxNov 10, 2024 · 44 KB
GO2526 Scope A6 Swifterbant - LemmerpdfNov 10, 2024 · 349 KB
bijlage B - Uniform Europees Aanbestedingsdocument - perceel A6pdfNov 10, 2024 · 2098 KB
42 Eisen Voertuigkering Versie 4pdfNov 10, 2024 · 564 KB
GO2526 Scope A6 Lelystad - Lelystad NoordpdfNov 10, 2024 · 128 KB

12Legal themes that may be relevant here

13Frequently asked questions

What is the specific scope of the works for the A2 and A6?
The works include maintenance of the asphalt, specifically replacing the surface course and repairing the binder course where necessary. Additionally, it concerns maintenance of structures and other objects such as vehicle barriers.
What exceptions to the repetitive works are there within the contract?
Although most tasks are repetitive, the widening of connection curve R at Knooppunt Oudenrijn (A2) and the replacement of six culverts (A6) require the development of a final design.
Which contract form applies to lots A2 and A6?
Because a detailed design is sufficient for the majority of the scope, an Engineering and Construct (E&C) contract form applies to both lots.

Automatically compiled from the official tender data and documents.

14Estimated value versus the market

p25
€ 1,4 mln
median
€ 3,6 mln
p75
€ 9,1 mln
deze opdracht

Gegunde waarden in CPV 45 · werken n=3159