ClosedWorksMarktconsultatieGreen

31178770 Market consultation tender Dike Strengthening IJmuiden

Rijkswaterstaat Programma's, Projecten en Onderhoud · Marktconsultatie · 1 lots · 349846
Type
Works
45240000
Estimated value
Not published
To deadline
Ongoing
Knock-outs
n/a
exclusion grounds
Award basis
Best price-quality ratio
Assess manuallyconfidence moderate

This concerns a market consultation for the dike strengthening of three dike sections in IJmuiden to comply with the Water Act. The assignment is expected to be tendered in 2025 and must be completed by the end of 2031 at the latest.

Works · Marktconsultatie · National procedure

Sustainability countsComplete timeline
Contract type
Works
Marktconsultatie
Estimated value
Estimate not published
Submission deadline
Ongoing
Scope
National
National procedure
Lots
1
1 lots
Main CPV code
Location
Netherlands
CharacteristicsCPV 45WorksGreen / SPP

01What is being requested

Realization of approximately 900m dike reinforcement in dike sections 2, 4 and 5 in accordance with the Preferred Alternative and Water Project Plan. The assignment includes earthworks, design and execution of the reinforcement, including adjustments to roads, road layout and sustainability measures such as charging stations.

This concerns a market consultation as preparation for the tender ‘Dike Strengthening IJmuiden’. The project concerns the realization of approx. 900m of dike reinforcement in accordance with the established Preferred Alternative (VKA) and Water Project Plan, future-proof design and execution of earthworks in the current dike alignment. As additional ambitions to the scope, works such as a condition inspection, adjustment of road surfacing, implementation of the project's sustainability objectives, such as material reuse and the construction of charging infrastructure, are applicable.

45240000Works
131178770 Market consultation tender Dike Strengthening IJmuiden

02Strategic insight

Strategic insight · AI analysis
Focus on the logistical challenges regarding supply by ship and the limited space on the dike sections. Anticipate the sustainability objectives such as the reuse of material and the deployment of electrified equipment. Ensure a strong strategy regarding stakeholder management due to the complex environment near the locks.
Read automatically from the tender documents using AI. Always verify against the original documents.

03Points of attention

Important · 6
The access to work sites and supply of material must primarily take place via water.Important
Account must be taken of the limited load capacity of the lock heads in IJmuiden.Important
The accessibility of the construction sites must be maintained as much as possible during the project.Important
There is a major challenge at dike section two due to the presence of residents and stakeholders.Important
The uniform appearance of the environment must be maintained in accordance with the municipality's customer requirements.Important
Provisions must be made for transshipment facilities for the demobilization of equipment and materials.Important

04Process & timeline

Publication of tender on TenderNed
Q3 2025
Award
Q2 2026
Execution completed
Q4 2031

05Value in context

Estimate not published

The contracting authority did not publish an estimated value — common for a large share of contracts. The EU threshold for werken is € 5,54 M, for reference.

06Likely competitors

#Likely bidderFitWins
1Boskalis Nederland B.V.SME9969×
2KWS Infra B.V.SME9792×
3Combinatie Heijmans - SWARCOUnknown9773×
4BAM Infra B.V.SME9777×
5Heijmans Infra B.V.SME9765×
6ENGIE Infra & Mobility B.V.SME9769×

07Tender documents

31178770 Sfeerverslag marktconsultatie dijkversterking IJmuidenpdfNov 13, 2024 · 153 KB
31178770 DVIJ MarktconsultatiedocumentpdfSep 19, 2024 · 447 KB
TN486552 - EF04 Vooraankondiging die alleen ter informatie wordt gebruikt - algemene richtlijn 20240919154112pdfSep 19, 2024 · 6 KB

08Legal themes that may be relevant here

09Frequently asked questions

What is the scope and objective of the Dike Strengthening IJmuiden project?
The project involves the realization of approximately 900 meters of dike reinforcement in accordance with the established Preferred Alternative (VKA) and Water Project Plan. The objective is the future-proof design and execution of earthworks in the current dike alignment.
Which additional works are part of the project scope?
In addition to the dike reinforcement, works apply for a condition inspection, the adjustment of the road surfacing, the implementation of the sustainability objectives (such as reuse of material) and the construction of charging infrastructure.
What was the purpose of the market consultation for this project?
The market consultation served as preparation for the tender to inform market parties about the dike strengthening task, approach and planning, and to collect input from the market for the further definition of the contract and the tender.

Automatically compiled from the official tender data and documents.

10Estimated value versus the market

p25
€ 1,4 mln
median
€ 3,6 mln
p75
€ 9,1 mln
deze opdracht

Gegunde waarden in CPV 45 · werken n=3159