31137594 Realisation Main Waterway Lemmer – Delfzijl (HLD) renovation canals, phase 1
Rijkswaterstaat Programma's, Projecten en Onderhoud · Competitive dialogue · 347266
5
5 of 6 core insights found
Measures presence, not accuracy · documents remain authoritative
ScopeAdvicePoints of attentionSuitability requirementsAward criteriaTimeline
Type
Works
Estimated value
Not published
To deadline
Ongoing
Knock-outs
0
exclusion grounds
Award basis
Best price-quality ratio
Assess manuallyconfidence high
This tender concerns the design and execution of renovation works on banks, guiding works and mooring facilities in the main waterway Lemmer – Delfzijl. The procedure follows a competitive dialogue with specific requirements for technical competence and project management.
Works · Competitive dialogue · European procedure
EuropeanComplete timeline
CharacteristicsCPVWorksEU tender
01What is being requested
Realisation of the renovation of canals, phase 1, consisting of the design and execution of the replacement of banks, the realisation and replacement of guiding works and the realisation and replacement of mooring facilities across nine locations.
Design & Construct (D&C) Contract Realisation Main Waterway Lemmer – Delfzijl (HLD) renovation canals, phase 1 2025-2027
02Strategic insight
Strategic insight · AI analysis
Ensure a strong reference assignment of at least € 14 million where you held ultimate responsibility. Check whether your experience with waterway works explicitly meets the class IV requirement. Pay close attention to the digital signature in accordance with the applicable EU regulation during application.
03Points of attention
Important · 5
The assignment is carried out via a competitive dialogue.Important
All works must be performed on the basis of a project management system certified according to NEN-EN-ISO 9001.Important
The assignment is awarded in the form of a design & construct contract under the conditions of UAV-GC 2005.Important
Documents that must be signed must be provided in pdf format with a qualified electronic signature.Important
An additional self-declaration must be attached upon application.Important
04Can I take part?
Technical — In the five-year period preceding the deadline for receipt of requests to participate, at least one assignment in the construction sector (civil engineering, building & utilities, installation technology) carried out with an agreed amount or invoiced amount equal to or greater than € 14,000,000.00 (excluding VAT), whereby the entrepreneur was responsible for the daily organization and le
Technical — In the five-year period preceding the deadline for receipt of requests to participate, experience gained in performing works in a waterway, at least suitable for class IV vessels.
05Exclusion grounds
Exclusion grounds — consult the ESPD
- No specific exclusion grounds were extracted. In a European tender, the mandatory and discretionary grounds of art. 2.86/2.87 of the Dutch Procurement Act almost always apply — check the European Single Procurement Document (ESPD).
06Process & timeline
Application phase
16-09-2024
Information meeting
Application phase
26-09-2024
Deadline for submission of requests for further information
Application phase
03-10-2024
Publication of memorandum of information application phase
Application phase
10-10-2024
Deadline for receipt of requests to participate
Selection phase
11-10-2024
Opening digital vault in TenderNed with requests to participate
Selection phase
17-10-2024
Sending notification of selection decision
Dialogue phase
25-10-2024
Opening data room
Dialogue phase
14-11-2024
General information meeting
Dialogue phase
21-11-2024
Deadline for submission of request for further information
Dialogue phase
28-11-2024
Provision/publication of memorandum of information
Dialogue phase
05-12-2024
Deadline for submission of narrowing-down product
Dialogue phase
19-12-2024
Sending narrowing-down decision
Dialoogfase
14-01-2025
Verzenden uitnodiging tot dialooggesprekken
Dialoogfase
30-01-2025
Dialooggesprekken tweede fase dialoog, eerste ronde
Dialoogfase
13-02-2025
Dialooggesprekken tweede fase dialoog, tweede ronde
Dialoogfase
25-02-2025
Uiterste datum indienen verzoek om nadere inlichtingen
Dialoogfase
11-03-2025
Verstrekken/publicatie nota van inlichtingen, afsluiten dialoog en verzenden uitnodiging tot inschrijving
Inschrijvingsfase
01-04-2025
Uiterste datum ontvangst van de inschrijvingen
Beoordelingsfase
02-04-2025
Openen digitale kluis in TenderNed met inschrijvingen
Beoordelingsfase
08-05-2025
Verzenden gunningsbeslissing
07Value in context
Estimate not published
The contracting authority did not publish an estimated value — common for a large share of contracts. The EU threshold for werken is € 5,54 M, for reference.
08Bidders in this segment
#Likely bidderFitWins
1Dynniq Nederland B.V. potentialSME370×
2Combinatie Witteveen+Bos Raadgevende ingenieurs BV / HaskoningDHV Nederland BV potentialSME350×
3SPIE Nederland B.V. potentialSME350×
4DEME Infra Marine Contractors BV potentialSME340×
5Boskalis Nederland B.V. potentialSME340×
6B.V. Aannemingsbedrijf De Klerk potentialSME340×
09Tender documents
TN482493 - EF38 Aankondiging van wijziging van een opdracht - algemene richtlijn 20260305075913pdfMar 6, 2026 · 231 KB
TN482493 - EF38 Aankondiging van wijziging van een opdracht - algemene richtlijn 20260304085649pdfMar 5, 2026 · 231 KB
TN482493 - EF38 Aankondiging van wijziging van een opdracht - algemene richtlijn 20251201083117pdfDec 2, 2025 · 13 KB
TN482493 - EF38 Aankondiging van wijziging van een opdracht - algemene richtlijn 20251128083030pdfNov 30, 2025 · 13 KB
TN482493 - EF38 Aankondiging van wijziging van een opdracht - algemene richtlijn 20251126105944pdfNov 27, 2025 · 12 KB
TN482493 - EF29 Aankondiging gegunde opdracht - algemene richtlijn, standaardregeling 20250624112146pdfJun 25, 2025 · 12 KB
Nota van inlichtingen 2024-10-01-1pdfOct 1, 2024 · 2 KB
31137594 Presentatie algemene inlichtingen bijeenkomst 16-09-2024pdfOct 1, 2024 · 2458 KB
31137594 1ste Nota van InlichtingenpdfOct 1, 2024 · 97 KB
Verslag Inlichtingenbijeenkomst 16-9-2024pdfOct 1, 2024 · 63 KB
31137594 - bijlage E AanbestedingsleidraaddocxAug 30, 2024 · 34 KB
31137594 - bijlage D AanbestedingsleidraaddocxAug 30, 2024 · 38 KB
10Legal themes that may be relevant here
Advies 426> Het betreft een Europese openbare procedure voor WMO-vervoer, leerlingenvervoer, participatiewetvervoer en lokaal vervoer, plus Advies 84> Openbaar nationale aanbestedingsprocedure voor een raamovereenkomst voor vertaaldiensten. IIB dienst en gebondenheid aan algemenAdvies 83> Openbaar nationale aanbestedingsprocedure voor een raamovereenkomst voor vertaaldiensten. IIB dienst en gebondenheid aan algemenAdvies 290> Meervoudig onderhandse aanbesteding van RAW-raamovereenkomst met een looptijd van één jaar voor rioolreiniging en rioolinspectieAdvies 618> De klacht ziet op Europese openbare aanbestedingsprocedure voor een overheidsopdracht van levering van turnkey Consoleboten incl
11Frequently asked questions
What is the nature of the assignment for the renovation of the canals?
The assignment concerns a Design & Construct (D&C) Contract for the realisation of the Main Waterway Lemmer – Delfzijl, specifically focused on the renovation of canals in phase 1 for the period 2025-2027.
What process management control is expected from the contractor?
The contractor is responsible for project management (PM), project control (PB), quality management (KM), integrated safety management (IV) and risk management (RM), including the drafting of a project management plan and a risk register.
Which employment condition requirements must the contractor meet?
The contractor must comply with the Foreign Nationals Employment Act (Wet arbeid vreemdelingen (AV)) and specific employment condition provisions (AB), whereby information obligations, checks and a forwarding obligation for wage claims apply.
Which technical elements are part of the system definitions?
The system definitions include, among others, bank works, guiding works, mooring facilities and area data, with specific attention to the realisation phase (safety, nuisance, cables & pipelines) and the usage phase.
Automatically compiled from the official tender data and documents.